[tab title=”About CMRL”] The Government of Tamil Nadu created a Special Purpose Vehicle (SPV) for implementing the Chennai Metro Rail Project. This SPV named as “Chennai Metro Rail Limited” was incorporated on 03.12.2007 under the Companies Act. The Company is a Joint venture between the Government of India(GoI) and the Government of Tamilnadu(GoTN). Both the Partners have a 50% stake in the Company. [/tab]
[tab title=”Timeline”]

[AdsWithin]The construction started on 10 June 2009 with the piling work for the elevated viaduct between Koyambedu and Ashok Nagar stretch. Construction is expected to be fully completed by February 2015. The first section to be opened will be on Line 2 between Koyambedu and St. Thomas Mount and this stretch is likely to be in operation by 2013. The construction work on the project was suspended on 9 August 2012, following an accident that killed a worker and injured six others, a day earlier. The work resumed after safety audit across its 32 stations was completed.

The tunnelling work began on 28 July 2012 at Nehru Park by means of twelve tunnel boring machines (TBMs) imported from China. Two parallel tunnels, 14.05 metres apart, were drilled at a depth of about 20 m for a length of 36,308 m. The depth of the tunnels will vary from 15 metres to 17 metres from the ground. The tunnel will have an outer diameter of 6.2 metres and an inner diameter of 5.8 metres. It will start at a depth of 9 metres from the surface.

The project is estimated to cost around INR146 billion (US$2.4 billion) for the two corridors totalling 45 km. However, the previous estimate in 2007 was INR95.65 billion (US$1.6 billion). But it is likely to increase by 23% to INR180 billion (US$3.0 billion)Tamil Nadu government in 2012–13 budget said global bids have been invited for implementing Phase I, covering 57 km and estimated to cost Rs 85 billion. The Underground tunnelling will cost about INR 3 billion per kilometre, whereas elevated track will cost about INR 1 billion per kilometre. The estimated construction cost of underground and elevated station will be INR 1 billion and INR 3 billion, respectively.

2008

2009

2010

2011

2012

2014

Source: Wikipedia

[/tab]
[tab title=”Route Map”]
The Two Lines of Metro Currently Under Construction are:

LINE-1:
Washermenpet – Broadway (Prakasam Road) – Chennai Central Station – Rippon Building – along Cooum River – Government Estate – Tarapore Towers – Spencers – Gemini – Anna Salai – Saidapet – Guindy – Chennai Airport.

LINE-2:
Chennai Central – along EVR Periyar Salai – Vepery – Kilpauk Medical College – Aminjikarai – Shenoy Nagar – Annanagar East – Anna Nagar 2nd avenue – Tirumangalam – Koyambedu – CMBT – along Inner Ring Road – Vadapalani – Ashok Nagar – SIDCO – Alandur – St. Thomas Mount.