Chennai Metro’s TBM Kurinji broke through at Srinivasa Nagar on Friday, 351 days after it set off from Kolathur, finishing a 1.08 km tunnel on the Madhavaram-Sholinganallur line.
More than 70 borewells and open wells sit above the route Kurinji took. The tunnel boring machine passed under or beside all of them on its way from Kolathur to the north shaft of Srinivasa Nagar station, where it broke through on Friday, 13 November. Chennai Metro Rail Limited (CMRL) said the drive was completed without disrupting traffic or the movement of people in what it called a densely populated residential area.
The drive began on 27 November 2025.
The numbers
Hard rock, a tight curve and wells overhead
When CMRL launched Kurinji from the south shaft of Kolathur station in November last year, its release described a 1,060 m run through Grade 5 and Grade 4 rock that included a sharp 230 m curve. The finished tunnel came to 1.08 km. On the way the machine moved from soil and weathered rock into hard rock, under a residential stretch dotted with borewells and open wells.
Kolathur is one of the north Chennai stops on the line, and Srinivasa Nagar is its neighbour on the underground section. With this drive done, Kurinji’s bore between the two stations is complete.
CMRL Managing Director Ashish Chatterjee and Director (Projects) T Archunan were at the breakthrough with executives of the contractor, Tata Projects, and the project’s general consultants.
Where this tunnel fits on Corridor 5
Corridor 5 runs 47 km from Madhavaram in the north to Sholinganallur on the IT corridor. Only 5.8 km of it is underground; the remaining 41.2 km runs on viaduct. CMRL assigned four machines to that underground stretch, and the names come from the tinai, the regions of Sangam poetry: குறிஞ்சி (Kurinji, the hills), முல்லை (Mullai, the forest), மருதம் (Marutham, farmland) and நெய்தல் (Neithal, the coast).
Mullai went first. It started from the Kolathur ramp on 23 May 2025 and broke through at Kolathur station’s north shaft after a 246 m drive with just 1.8 m of ground above it and a downward gradient of 3.8%. The same day Kurinji was launched from the station’s south shaft, which CMRL described as the first time in India that one TBM was launched and another broke through at the same underground station.
The third, which CMRL’s 1 October release names Maruthan, broke through at Villivakkam station on 30 September 2026.
Precast elements cast for the Ullagaram-Sholinganallur viaduct package ECV-03, now 100% complete, according to CMRL’s release of 13 October.
At the southern end the work is above ground. The HCC-KEC consortium finished casting the last U-girder for that package in October, and CMRL said erection of the remaining U-girders and the station entry and exit structures came next. CMRL has not given a date for passenger service on Corridor 5 in the releases checked for this story.
For Context
Phase 2 tunnelling picked up pace this autumn. At the turn of the month CMRL logged three breakthroughs in three days: Kaveri at KMC station and Adyar at RK Salai on Corridor 3, and the Corridor 5 machine at Villivakkam. Adyar’s drive, under Peters Bridge and the shops of Royapettah High Road, took 277 days. On Corridor 3, the Kellys-Taramani section alone has 12 km underground and eight TBMs mobilised by Larsen & Toubro. The first Phase 2 trains to carry passengers ran on Corridor 4, where Stage 1A service began in October 2026.
Checked against official sources on 15 November 2026.
Sources
- Statement on TBM Kurinji breakthrough at Srinivasa Nagar, 13 November 2026 (Chennai Metro Rail Limited)
- Press Release P.R. No. 97/2025: TBM Mullai breakthrough at Kolathur and TBM Kurinji begins tunnelling to Srinivasa Nagar, 29 November 2025 (CMRL)
- Press Release P.R. No. 65/2026: Phase-II hat-trick of TBM breakthroughs in three days, 1 October 2026 (CMRL)
- Press Release P.R. No. 67/2026: Precast construction complete for Corridor-5 ECV-03 (Ullagaram-Sholinganallur), 13 October 2026 (CMRL)
- Press Release: Phase 2 Corridor-4 Stage 1A passenger service, 10 October 2026 (CMRL)