Chennai Metro Rail has handed Capacite Infraprojects a ₹446.88 crore contract to put up four buildings around the Phase-2 Thirumangalam station on Corridor 5.
The site is 3.85 acres. That is the whole of the land CMRL is developing at Thirumangalam (திருமங்கலம்), and the company calls it one of the major transit-oriented development projects in its Phase-2 network, according to its press release of 12 November.
The agreement was signed in the presence of CMRL Managing Director Ashish Chatterjee, with the company’s directors and senior officials attending. The contract value includes GST. Capacite has 24 months from the start of work to finish.
Four towers either side of the viaduct
The buildings sit on both sides of the Corridor 5 station, along the line of the viaduct, and they are not the same size. Towers A and C each get three basements and a ground-plus-nine structure above them. Tower B is ground plus nine with no basement, and Tower D is a low block of ground plus two. The Phase-2 Thirumangalam station itself lies between Towers B and C, so the release describes passengers walking from the platforms straight into the complex, with public transport and the buildings in one place rather than across a road.
| Building | Basements | Above ground |
|---|---|---|
| Tower A | 3 | Ground plus 9 |
| Tower B | None listed | Ground plus 9 |
| Tower C | 3 | Ground plus 9 |
| Tower D | None listed | Ground plus 2 |
Source: Chennai Metro Rail Limited press release, 12 November 2026
What the floors will hold is not spelt out. The release does not say whether the space is for offices, shops or homes, or who will lease it.
Precast elements cast for the Ullagaram to Sholinganallur package of Corridor 5, which CMRL said in its 13 October release had reached 100% of its precast work.
Where Corridor 5 stands
Thirumangalam is one stop on Corridor 5, the Phase-2 line whose southern package from Ullagaram to Sholinganallur finished its last U-girder casting in October. The HCC-KEC consortium cast 892 U-girders there, the highest count among Phase-2 packages, according to CMRL. Erection of the remaining girders and construction of the station entry and exit structures were the next steps it listed.
The property contract is a separate job from the viaduct, let to a different company, and its money is counted separately from the line itself.
For commuters on the existing line at Thirumangalam, the change will show first as a construction site beside the new station, since the towers and the Phase-2 platforms share one plot. CMRL has not said when the towers will open to tenants. On the contract’s own clock, the earliest finish is two years after work begins.
How we worked this out
The tower heights, basements, site area, contract value and 24-month deadline are taken from CMRL’s 12 November release. The Corridor 5 girder and precast counts come from its 13 October release. The release gives no basement for Towers B and D, so the table marks them as none listed. No figure here is our own estimate.
Checked against official sources on 15 November 2026.
Sources
- CMRL awards contract for property development buildings at Thirumangalam, press release, Chennai Metro Rail Limited, 12 November 2026
- CMRL precast milestone for Phase-2 Corridor-5 ECV-03 (Ullagaram to Sholinganallur), press release No. 67/2026, Chennai Metro Rail Limited, 13 October 2026
- Phase II, Chennai Metro Rail Limited